Hi Sathish
Thanks for the reply.
Ok so we see here the BPEMUWL Connector is failing.
The two key points of reference here include:
- You have the bpm task been created and assigned to you
- The connection between bpm and the uwl working.
For 1), go to Manage Processes, select the row showing your process instance and press the Related Tasks button. In related tasks check that a task is listed, that it is in Ready status, and then select the task row and check that you are a nominated owner of the task. If 1) is all ok then you can check 2).
To check 2) you need to get to the UWL admin iview in the portal - it's in portal menu path System Administration > system configuration > workflow administration. Check the system alias used for the BPEM uwl connector. Make sure it is showing as registered, and if that looks ok check out the system alias itself is ok and working in the portal and that your user mapping is working properly between the portal and bpm.
http://help.sap.de/saphelp_nwce72/helpdata/en/0e/57827af0e34edfacd4c82edeb6acca/content.htm
Kindly update me as per your findings.
Kind Regards & All The Best
Troy Cronin - Enterprise Portal Support Engineer
Follow Troy Cronin